Reseat or Install an SP Tray

  1. Before installing a new SP tray into an empty bay, open the ejector latches so that they are fully open.
  2. Slide the SP tray into its slot in the server until the ejector latches begin to engage.

    Ensure that the tray aligns with the alignment block on the left side of the chassis and the metal tab on the right side of the chassis before latching the tray in place. If you do not properly align the tray, the latch will not engage.

  3. Press the ejector latches back together toward the center of the SP tray, and then press the latches firmly against the SP tray to fully seat the tray back into the server.

    The latches should click into place when the tray is fully seated in the server.

  4. Reinstall the SPs you removed from the SP tray.

    See Servicing SPs.

  5. Reinstall the cables you removed from the NET MGT and SER MGT ports.

    Ensure that you install the cables in the same ports from which you removed them.

  6. Switch on the appropriate PDU circuit breakers and power on the server.

    See Returning the Server to Operation.

  7. Verify that the fault has been cleared and the replaced component is operational.

    See Verify That a Fault Has Been Cleared.

  8. Return the replaced component to Oracle.

    See Prepare a Component for Return to Oracle.