Return the Server to Operation

  1. If removed, install the top cover.

    Position the top cover on the chassis, and tighten the two green captive screws on the rear of the top cover (Installing the Top Cover).

    Figure 6-1  Installing the Top Cover


    image:Figure showing top cover installation
  2. Install the server into the rack.

    Refer to the Sun Netra T5440 Server Installation Guide (820-4442).

  3. Cable the server.

    Refer to the Sun Netra T5440 Server Installation Guide (820-4442).

  4. Power on the server.

    Refer to the Sun Netra T5440 Server Installation Guide (820-4442).