Returning the Switch to Operation
These topics explain how to return the switch to operation after you perform service
tasks.
|
|
|
1.
|
Retrieve the power cord and if necessary, the SER MGT cable. Then,
power on the power supply if you serviced these components:
-
Power supply
-
Switch replacement
|
|
2.
|
Configure the switch and connect the data cables if you serviced this
component:
|
|
3.
|
Install the snap bracket.
|
|
4.
|
Install the air duct assembly if you serviced the components in Step 1
or these components:
|
|
5.
|
Verify the installation of the component, if you serviced the
components in Step 1, Step 2, or Step 4.
|
|
|