Oracle® InfiniBand Switch IS2-46 Service Manual

Exit Print View

Updated: September 2016
 
 

Returning the Switch to Operation

These topics explain how to return the switch to operation after you perform service tasks.

Step
Description
Link
1.
Retrieve the power cord and if necessary, the SER MGT cable. Then, power on the power supply if you serviced these components:
  • Power supply

  • Switch replacement

2.
Configure the switch and connect the data cables if you serviced this component:
  • Switch replacement

3.
Install the snap bracket.
4.
Install the air duct assembly if you serviced the components in Step 1 or these components:
  • Battery

  • Fan module

5.
Verify the installation of the component, if you serviced the components in Step 1, Step 2, or Step 4.

Related Information