(Optional) Assemble the Optical Fiber SFP+ Cables

If the optical SFP+ cables are unassembled, you must assemble the cables before connecting them to the switch.


Note -  The ends of the optical fiber cable and the receptacles of the transceivers must be clean and optically clear before assembly. Do not remove the protective caps from the optical fiber cable or the plugs from the transceivers until instructed to do so.
  1. Identify the prerequisite and subsequent installation tasks that you must perform in conjunction with this task.

    See Servicing Data Cables.

  2. Remove the SFP+ optical transceivers and fiber optic cables from their packaging.
  3. Remove the plug from an SFP+ optical transceiver.
  4. Remove the caps from an LC connector of the fiber optic cable.
  5. Holding the shafts of the LC connector, insert the LC connector into the receptacles of the SFP+ optical transceiver.
    image:Illustration shows the LC transceiver and LC connector                             assembling.

    Note -  The LC connector and SFP+ receptacles are keyed for proper fitting.
  6. Push the connector into the transceiver until it clicks.
  7. Repeat Step 3 through Step 6 for the other end of the cable.
  8. Repeat Step 2 through Step 7 for any additional optical fiber SFP+ cables to be installed.
  9. Install the cable or return to that task.

    See Install a Data Cable.