Prepare to Power Off the Switch
Perform this task before powering off the switch for a switch replacement.
Note -
The steps of this task are a generalization of what is to be done. For more
thorough instructions on how to accomplish these steps, refer to the
Oracle EDR InfiniBand Switch and Virtualized I/O Systems
Administration Guide, the Oracle Fabric Manager 5.0
Administration Guide, and the Oracle Fabric OS 1.0
Administration Guide.
-
Notify affected users that the switch is to be shut down.
-
Access the SCP on the switch to be removed.
See Access the SCP (RJ-45 Port).
-
If the switch to be removed is configured with the master Subnet Manager,
initiate a handover to the standby Subnet Manager.
Refer to the Oracle Fabric Manager 5.0 Administration
Guide. Wait for any handover to complete.
-
If the switch to be removed is configured with any Subnet Manager, set the
priority to the lowest.
Refer to the Oracle Fabric Manager 5.0 Administration
Guide.
-
Create a backup of the switch configuration for the switch to be
removed.
-
On the switch, create a backup of the Oracle Fabric Manager
configuration.
Refer to the Oracle Fabric Manager 5.0 Administration
Guide.
-
On the switch, create a backup of the Oracle Fabric OS
configuration.
Refer to the Oracle Fabric OS 1.0 Administration
Guide.
-
Access the SP.
See Access the SP (RJ-45 Port)
-
Write the SEFOS configuration to Oracle ILOM, and create a backup of
the Oracle ILOM configuration.
This backs up the SEFOS configuration. Refer to the Oracle
EDR InfiniBand Switch and Virtualized I/O Systems Administration
Guide.
-
Transfer the backup files to a safe place.
-
Power off the switch.
See Power Off a Power Supply.