Install a Power Supply

Installing a power supply is a hot-swap operation. You do not need to power off the server before installing the power supply.

  1. If you are replacing a faulty power supply, remove the faulty component.

    See Remove a Power Supply.

  2. Align the power supply to the location where it installs into the server.

    The PDB connector is toward the server, and the release tab is on the right.

  3. Slide the power supply into the server until the power supply seats, and the release tab clicks.
    image:The illustration shows installing the power supply.
  4. Connect the power cord.
  5. If you installed a power supply as part of another component's removal or installation procedure, return to that procedure.

    See Component Service Task Reference for assistance.

  6. Complete these tasks in this order to finish the installation.

    See:

Related Information