Installing a power supply is a hot-swap operation. You do not need to power off the server before installing the power supply.
The PDB connector is toward the server, and the release tab is on the right.
For AC power supply, see Connect AC Power Cords.
For DC power supply, see Assembling and Connecting DC Power Cords in Netra SPARC S7-2 Server Installation Guide.
See Component Service Task Reference for assistance.
See: