Go to main content
Netra SPARC S7-2 Server Service Manual

Exit Print View

Updated: February 2017
 
 

Verify a Power Supply

After you install a power supply, you can verify its functionality.

  1. Access Oracle ILOM.

    See Log In to Oracle ILOM (Service).

  2. Reset the power supply.
    -> set /SYS/PSx clear_fault_action=true
    Are you sure you want to clear /SYS/PS0 (y/n)? y
    Set 'clear_fault_action' to 'true'
    ->

    where x is 0 (lower power supply) or 1 (upper power supply).

  3. Verify that the power supply is no longer considered faulty, then return to this procedure.

    See Locate a Faulty Power Supply.

  4. Verify the voltage output.
    -> show /SYS/PS0/V_+12V value
     /SYS/PS0/V_+12V
     	Properties:
     		value = 12.031 Volts
    ->