Installing the PDB is a cold-service operation. You must power off the server before installing the PDB.
If you are replacing the PDB, remove the faulty or obsolete PDB first, then return to this procedure, Step 2. See Remove the PDB.
If you are installing the PDB as part of another component's removal or installation procedure, go to Step 2.
The bus bars are forward and down.
If you installed the PDB as part of a replacement operation, go to Step 8.
If you installed the PDB as part of another component's removal or installation procedure, return to that procedure. See Component Service Task Reference for assistance.
Install all DIMMs.
Install all fan modules.