Install the Battery

  1. Remove the replacement battery from its packaging.
  2. Press the new battery into the battery holder with the positive side (+) facing the server chassis side wall.
  3. Install the PCI mezzanine.

    See Install the PCI Mezzanine.

  4. Return the server to operation.

    See Returning Server to Operation.


    Note - If the SP is configured to synchronize with a network time server using the Network Time Protocol, the ILOM SP clock will be reset as soon as the server is powered on and connected to the network.
  5. If the SP is not configured to use NTP, you must reset the ILOM service processor clock using the ILOM CLI or the web interface.

    For instructions, refer to the ILOM 3.0 documentation.