Install the Power Distribution Board

  1. Remove the replacement power distribution board from its packaging and place it on an antistatic mat.
  2. Lower the power distribution board into the chassis, aligning the board???s holes with the standoffs in the chassis.
    image:Figure showing how to place the PDB into the system.
  3. Install the screws firmly to secure the power distribution board to the chassis.

    There are five screws that secure the power distribution board to the chassis, and four screws that connect it to the bus bar.


    image:Figure showing how to secure the PDB screws.
  4. Connect the four cables to the power distribution board.
    image:Figure showing how to connect cables to the PDB.
  5. Install the following components:
  6. Return the server to operation.

    See Returning Server to Operation.